The team responsible for administering the council's duties in regards to Street Works and associated legislation is the Traffic Team.
The council operates a permit scheme, to make sure that network activities are undertaken safely and efficiently for all our highway users. We can also enable people to make the right transport and route choices. We want those choices to be first and foremost; efficient, sustainable, healthy and convenient.
Permit applications for EV charge point installations in Dorset must contain enough detail for the highway authority to fully understand the nature and impact of the proposed works.
Each application should include clear and accurate information about:
- what is being installed, what activities will take place, and how the work will be carried out
- the exact location, including coordinates, site plans, and any relevant photos or drawings
- proposed start and end dates, working hours, and any flexibility around these
- how traffic, pedestrians and cyclists will be safely managed during the works
- realistic estimates of how long each phase of the works will take
- evidence of prior engagement, demonstrating that early coordination has taken place
Providing complete and accurate information helps ensure that applications can be assessed quickly and reduces the likelihood of delays or refusals.
Permit response timeframes
The council must respond to permit applications within the statutory timeframes set out in national guidance. For most applications, this is typically 2 to 5 working days, depending on the category of the works.
These timeframes apply to:
- initial permit decisions
- requests for further information
- variations or changes to existing permits
Submitting well‑prepared applications helps ensure decisions can be made within these statutory periods.
When permit applications might be refused
Permit refusal codes may be issued where an application does not meet the required standards or conflicts with earlier coordination. Common reasons for refusal include:
- insufficient or unclear information
- lack of evidence of prior engagement
- proposals that differ from what was agreed during pre‑application discussions
- conflicts with other planned works or network constraints
- non‑compliance with statutory guidance or local requirements
Refusal codes must be used in line with national guidance, ensuring transparency and consistency.
Applicants should review refusal reasons carefully and resubmit with the necessary corrections or clarifications.