While multi year funding settlements provide greater certainty, securing sufficient funding remains a challenge.
The Implementation Plan sets out how the strategy will be delivered, including schemes, funding, phasing and local priorities.
Delivery is phased across three periods:
- IP1 2026 to 2031 (ready to deliver schemes)
- IP2 2031 to 2036 (developing schemes)
- IP3 2036 to 2041 (long term projects)
Over 95 schemes are identified, including:
- new walking, cycling and wheeling routes
- road safety schemes
- bus priority measures
- EV infrastructure expansion
- rail improvements
- junction improvements and traffic management schemes
For individual schemes appropriate local consultation (including methods such as randomised sample surveys) will take place at the development stage.
Delivery of the first phase requires over £315.8 million and will depend on ongoing government funding, developer funding and continued support from our transport partners to deliver schemes.
Timeline:
- 2026 - LTP Baseline report
- 2030/2031 - Implementation Plan 1 Monitoring report
- 2035/2036 - Implementation Plan 2 Monitoring report
- 2040/2041 - Implementation Plan 3 Monitoring report
Estimated funding for IP1:
- Dorset Council £203.5 million
- BCP Council £112.3 million
- Total £315.8 million