The CIL charging schedules for West Dorset, Weymouth and Portland were adopted in October 2015.
In setting the CIL charging rates, we have taken into account evidence on the impact of development viability and the costs of providing infrastructure to support new development. Consultants BNP Paribas were instructed to test the ability of a range of development types to yield contributions to infrastructure requirements through the Community Infrastructure Levy. Levels of CIL have also been tested in combination with the councils' other planning requirements, including contributions towards the provision of affordable housing. Consultation with local developers has also helped inform the development of the levy.
The various stages in the production of the CIL charging schedules and the consultations which took place through the process are listed below along with the documents that have been prepared and consultation responses received at each stage.
Please be aware that the Regulation 123 Lists were revised in November 2016. Please look at How will CIL be spent page for further information.
Adoption of the CIL charging schedules | Date |
---|---|
WDDC CIL Charging Schedule | October 2015 |
WDDC Regulation 123 List | October 2015 |
WPBC CIL Charging Schedule | October 2015 |
WPBC Regulation 123 List | October 2015 |
CIL Instalment Policy | October 2015 |
Map showing CIL charging areas | October 2015 |
CIL examination documents | Date |
---|---|
Inspector's Final CIL Report | August 2015 |
Letter 1 from PINS with estimated date for CIL Report | July 2015 |
Letter 2 from PINS with estimated date for CIL Report | July 2015 |
CIL Main Modifications consultation document | March 2015 |
CIL Main Modifications Consultation Summary | March 2015 |
CIL Modifications Response - Bourne Leisure Ltd | April 2015 |
CIL Modifications Response - Broadwindsor Group Parish Council | April 2015 |
CIL Modifications Response - Condor Ferries | April 2015 |
CIL Modifications Response - Crossways Parish Council | April 2015 |
CIL Modifications Response - Highways England | April 2015 |
CIL Modifications Response - Jonathan Orrell | March 2015 |
CIL Modifications Response - Natural England | April 2015 |
CIL Modifications Response - Scottish and Southern Energy | March 2015 |
CIL Modifications Response - C G Fry & Son Ltd | April 2015 |
CIL Matters Statement (MS/CIL16) | November 2014 |
Modifications to the CIL draft charging schedules | Date |
---|---|
Statement of Modifications to the CIL Charging Schedules | June 2013 |
CIL Modifications Consultation 2013 - Response by the Marine Management Organisation | July 2013 |
CIL Modifications Consultation 2013 - Response by McCarthy and Stone | July 2013 |
CIL Modifications Consultation 2013 - Response by McCarthy and Stone and Churchill Retirement Living Ltd | June 2013 |
CIL Modifications Consultation 2013 - Response by Savills | July 2013 |
CIL Modifications Consultation 2013 - Response by the Highways Agency | June 2013 |
Consultation on the draft CIL charging schedule | Date |
---|---|
WDWP Draft Charging Schedule | November 2012 |
WDWP Draft Charging Schedule Consultation Summary | November 2012 |
Response to Viability Issues raised - report produced by consultants BNP Paribas | November 2012 |
Consultation on the preliminary draft CIL charging schedule | Date |
---|---|
WDWP Preliminary Draft Charging Schedule | June 2012 |
WDWP Preliminary Draft Charging Schedule Consultation Summary | June 2012 |
West Dorset CIL viability report | Date |
---|---|
West Dorset CIL Viability Report | February 2012 |
West Dorset CIL Viability Report - Appendix 2 | February 2012 |
West Dorset CIL Viability Report - Appendix 3 | February 2012 |
West Dorset CIL Viability Report - Appendix 4 | February 2012 |
Weymouth and Portland CIL viability report | Date |
---|---|
Weymouth & Portland CIL Viability Report | March 2012 |
Weymouth & Portland CIL Viability Report - Appendix 2 | March 2012 |
Weymouth & Portland CIL Viability Report - Appendix 3 | March 2012 |