At the earliest design stage, developers should:
- check whether any PRoW crosses or runs close to the site
- understand how the site layout and construction could affect these routes
- consider how impacts can be avoided or reduced
- look for opportunities to improve active travel and connect homes to the wider network
- prepare an outline PRoW management plan
- seek to retain existing views and the character of the route with no net loss of rural paths
- consider impacts of more people on the network
The Definitive Map and Statement is the official legal record of all PRoW in Dorset and must be checked during site design. The Definitive Map team can advise where routes are unclear or uncertain.
If a path exists on the ground but is not recorded on the Definitive Map, early contact with the team is essential. Failure to identify a PRoW can cause delays or create future problems for homeowners.
Diversions created under planning legislation cannot introduce new obstructions, such as gates.